Leading Factors Contributing to the Generation of Claims in Indian Construction Industry-Consultant's Perception- Juniper Publishers
Juniper Publishers- Journal of Civil Engineering
Abstract
Claims frequently occur during the course of
construction projects in developing countries and Indian construction
industry has always been impacted and devastated by excessive number of
claims and disputes. This study is investigating the leading factors
contributing to the generation of claims and their sources in Indian
construction industry. Further, the study is conducted to determine the
frequency of occurrence of different claim types in Indian construction
projects, and to provide recommendations and suggestions to
avoid/mitigate these claims. The objectives of the study have been
achieved through a valid questionnaire that was distributed and obtained
from different consultant's construction organizations working in
Indian construction industry. The results showed that the most important
factors that contributed to the generation of claims are contactor
financial problem, excessive change orders by owner, slow decisions from
owner, poor planning and management by contractor, and delay caused by
the contractor. The results also showed that the most frequent claim
type is extra-work claim. Several recommendations for the owners and
contractors to mitigate claims occurrence are summarized at the end.
Keywords: Claim causes; Claim types; Dispute; Mitigate claims; Pivotal position
Abbreviations: DAB: Dispute Adjudication Board; EoT: Extension of Time
Introduction
Construction Industry plays a key role in the
economic development and growth of India and occupies a pivotal position
in the nation's development plans. The construction industry is the
second largest contributor to the GDP in India after the agriculture
sector. According to a report made by CIDC, the construction sector has
been contributing around 8 per cent to the nation's GDP. The Indian
construction industry is booming, and this is due to a growing economy
and demand, interest of foreign investors in India and ongoing major
developments in India with more developments to occur in the future [1].
However, this sector contribution is negatively affected by the
increasing number of claims as a result of the growing complexity of
projects.
Construction industry in most of the countries is
infamous for schedule and cost overrun, poor quality, large number of
disputes, and many other ills and this is truer in case of developing
countries such as India [2].
There are significant time and cost overruns in projects across
sectors, which lead to claims. Projects across different government
employers suffer from cost overrun of 50-100%, primarily driven by EoT
(Extension of time). In the recent years, all of the stakeholders in the
construction process have become increasingly concerned with
construction claims. That is attributed to the fact that construction
claims are found in almost every project. They are indispensable in the
construction projects, and mostly in nowadays, where the substantially
increasing volume of claims are the result of the rising complexity of
the projects, the price structure of construction industry and the legal
approach taken by a lot of owners and contractors [3].
In fact, there are few contracts in which there are no claims,
negotiations and settlement before the contract is finally closed.
However, financially strained Indian construction industry crisis are
driven by unsettled claims such as 85% of claims raised are still
pending and average settlement time is nearly 6 to 6.5 years. Employers
always take awarded claims to courts to delay payments and courts
normally uphold arbitrators' decisions.
It is important to have a staff that can recognize
claims at an early stage and know how to deal with them accordingly.
Recognizing claims at early stage requires understanding of the major
root causes of claims and this understanding must not just be limited to
senior management at the home office. Site supervisors and engineers
who deal with the day-to-day work must be 7 equally well informed in
how to recognize and identify issues that might give a rise to claims in
order to mitigate, avoid or manage them professionally.
Numerous research studies have been conducted on
claims and claim management in the developed and developing countries.
However, in India enough research studies are not reported on the above
stated aspect. Hence there is a need to conduct a research in this area
to understand in depth the root factors contributing to the generation
of claims in Indian construction industry, to identify the most frequent
claim types in Indian construction projects and to assist the
professionals in this industry for further development and growth in the
management of future projects.
Literature Review
Scholars through the past years defined claims in
different ways. Diekmann and Nelson defined claims as the seeking of
consideration or change, or both, by one of the parties to a contract
based on an implied or express contract provision [4].
According to Jergeas and Hartman, claim is the application by the
contractor for payment that arises other than under the ordinary
contract payment provisions [5].
Adrian classified claims into four major types: delay claims, scope of
work claims, acceleration claims and changing site conditions claims [6].
Zineldin in his study in the Emirates of Dubai and Abu Dhabi using data
from 124 claims, revealed that the types of claims in construction
projects in UAE can be classified into six main types: contract
ambiguity claims, delay claims, acceleration claims, changes claims,
extra-work claims and different site condition claims [7].
Chaphalkar and Iyer in their study of a total of 52 arbitration awards
in India found that, out of the 52 arbitration awards, 38 awards are
pertained to delay related claims [8].
Chaphalkar and Sandbhor in their study of total 23 arbitration awards
for Indian construction projects, a total of 419 claims leading to
construction disputes were studied. Nineteen percent of the claims were
variation claims, extra-work claims were 17% and escalation claims were
11% of the total number of claims studied [9].
Although the available literature review on claims in
India is less. The causes of claims have been investigated by many
scholars worldwide. Claims for added costs and extended performance time
can result from a variety of events during the course of a construction
project. The claims may be those of the project owner, the prime
contractor or by any of the project's trade contractors or suppliers.
Dickmann and Nelson have found that the most common causes for a
contract claim are design changes and errors. A comprehensive analysis
of claims indicated that 46% resulted from design errors. An additional
28% were due to either discretionary or mandatory changes. Thus 72% of
all contract claims can be traced to design changes, extra work, and
errors [4].
Zineldin in his study in the Emirates of Dubai and Abu Dhabi using data
from 124 claims, revealed that the most frequent causes of claims in
construction projects in UAE are: change orders, delay caused by owner,
oral change orders by owner, delay in payments by owner [7]. Abd El-Razek et al. [10]
reviewed the causes of claims in the international literature and then
modified these causes according to the Egyptian construction industry
using semi-structured interviews with 10 experts. The modified list
included 17 causes. Three case studies were utilized during his research
to further investigate the occurrence of each cause in the project. The
most frequent causes were: variations initiated by owner/consultant,
inferior quality of design, drawings and/or specifications, delays of
approval of shop drawings, instructions and decision making and
stakeholders involved in the project [10]. Enshassi et al. [11]
investigated 41 factors causing claims in Gaza strip, under four
categories: owner related factors, design and bill of quantities related
factors, contractual relationship related factors, and emergency cases
related factors and the results revealed the main causes of claims were
awarding bid to the lower bidder, border closures, residents'
interference during project implementation and road blockage and
difficulties in passing between cities and governorate [11].
Al-Mohsin studied 26 causes of claims in construction industry and
collected data from 45 projects with specific criteria in Oman [12].
He divided these factors into four categories based on the origin of
claims: owner related factors, consultant related factors, contractor
related factors and contract document related factors [12]. Sibanyama et al. [13]
during their study on causes of claims in the Zambian construction
categorized 20 causes of claims according to the 4 phases of a
construction project: pre tender; contract formulation; construction and
post construction phases [13]. Mohamed et al. [14]
investigated 31 factors causing claims in Egyptian construction
industry and concluded that the most disputable claim factors are
extension of time, delay interim payment from client, qualification of
team work, variations order by owner, poorly written contracts, late
supply of equipment and material, incomplete drawings and specification
and cooperation and communication nature [14].
Research Methodology
The work in the present paper was done in two stages,
the first stage, 39 claim causes and 8 claim types were identified. The
identification was done through a literature review and interviews with
experts in Indian construction industry. In the second stage a
questionnaire was developed to assess the perception of the consultants
towards the factors causing claims and the frequency of different types
of claims. The questionnaires were administered through convenience
sampling. In convenience sampling, a survey is conducted with
respondents who are easily accessible [15].
It is an appropriate method where sufficient information on population
size is not available, but like other non probability sampling, findings
may not be generalized to the population [16].
The questionnaire is divided into three main parts. Part one is related
to general information for both the company and the respondent.
Consultants were further requested to answer questions pertaining to
their experience in the construction industry, specialization and the
size of their organizations. The second part of the questionnaire
focused on causes of claims, which includes 39 identified causes of
claims in Indian construction projects [17]. These causes are classified into the following six major groups according to the source of claim:
Owner/Owner's representative related factors
Owner personality, delay in handing over site, delay
in payments to contractor, lack of staff experience for contract
provisions management, excessive change orders by owner, delays of shop
drawings approval by owner's representative, delay in approval of
completed work, slow decisions from owner, acceleration and stop and go
operation, and long line of authority in owner's organization.
Contractor related factors
Delay caused by contractor, poor planning and
management by contractor, contractor's financial problem, poor quality
of contractor's work, execution errors by contractor, and lack of
control over sub contractor.
Contract documents related factors
Poorly written contract and ambiguities, variations
between original and actual quantities, incomplete contract documents,
design error or omissions, and different types of contracts, and
discrepancies between contract documents.
Project related factors
Change scope of the project, different sub grade
conditions, complex execution of the project, and change location of the
project.
Contractual relationship related factors
Lack of coordination and communication among parties,
failure of participants to deal promptly with changes and unexpected
outcome, termination of contract by one of party, suspension of work by
one party, awarding bid to lowest bidder, and insufficient time for bid
preparation and inadequate investigation before bidding.
External factors
Force majeure, unexpected changes in exchange,
interest, and inflation rate, unexpected change in material price,
extreme weather conditions, unforeseen ground condition by all parties,
changes in government regulations and laws, and stakeholder
(beneficiaries, local community, authorities) interference.
The respondents were asked to indicate the degree of
contribution of each factor to the generation of claims in Indian
construction industry. The degree of contribution was categorized on a
five-point Likert scale as follows: Very high, high, moderate, low, very
low, on a 5 to 1 point scale.
Third part of the questionnaire was about the
frequency of different types of claims in Indian construction projects.
The eight types of claims identified were: Delay claims, changes claims,
extra-work claims, different site conditions claims, acceleration
claims, disruption claims, contract ambiguity claims and price
escalation claims. The respondents were asked to indicate the frequency
of occurrence of each type of claim. The frequency was categorized on a
five-point Likert scale as follows: Very frequent, frequent, medium,
low, rare. On a 5 to 1 point scale.
The respondents were also asked to highlight their recommendations to minimize/mitigate claims in Indian construction industry.
The survey instrument was pilot-tested to measure its
validity and reliability. The pilot study was conducted by distributing
the questionnaire to two panels of experts having experience in the
construction field to assess the questionnaire validity and provide
constructive feedback. The first panel, consisting of 8 experts (owners,
consultants, contractors), was asked to verify the validity of the
questionnaire content and its relevance to the research objective. The
second panel, consisting of two experts in statistics, was asked to
confirm that the instrument used was valid statistically, and that the
questionnaire design was well enough for the purpose of this research.
Experts’ comments and suggestions were accordingly incorporated to
ensure the validity and reliability of the questionnaire.
The research was carried out in India, one hundred
and fifty sets of questionnaires were distributed to the potential
respondents at all levels in the consultant's organizations within the
construction industry, and 89 responses have been received. Though the
sample size is relatively small, the quality of the responses was
considered to be highly reliable for the analysis due to relevant
industry experience.
Data Analysis
Calculation of relative importance index
The suggested claim causes and types in Indian
construction projects are ranked by the measurement ofthe relative
importance index. The relative index techniques have been widely used in
construction research for measuring attitudes with respect to surveyed
variables.
Several researchers used the relative importance index in their analysis. Chan & Kumaraswamy [15]
are of the opinion that the mean and standard deviation of each
individual factor is not suitable statistics to assess the overall
ranking because they do not reflect any relationship between them and
accordingly they have used the "relative importance index" (RII) method
to determine the relative ranking of factors. The RII is evaluated using
the following formula:
Relative Importance Index (RII)
Where W is the weighting given to each factor by the
respondent, ranging from 1 to 5, (n1=number of respondents for weight 1,
n2= number of respondents for weight 2, n3=number of respondents for
weight 3, n4= number of respondents for weight 4, n5=number of
respondents for weight 5).
A is the highest weight (i.e., 5 in the study) and N
is the total number of samples. The relative importance index ranges
from 0 to 1.
Research Results and Discussion
General characteristics of respondents
The questionnaire was sent out to a total of150
consultants, to assess their perception in ranking the identified causes
and types of claims in terms of their contribution and frequency using
an ordinal scale. A total of 89 filled the questionnaire. The response
rate is 59%. The respondents who are included in the survey have an
average of ten years of experience.
Claim causes
The causes under each group are ranked by the
measurement of relative importance index according to Eq. (1). The
ranking of relative importance index of the claim causes in Table 1
shows that contactor financial problem, excessive change orders by
owner, slow decisions from owner, poor planning and management by
contractor, and delay caused by the contractor are the top significant
factors. Moreover, change scope of the project, lack of control over sub
contractor, delay in handing over site, variations between original and
actual quantities, and poorly written contracts and ambiguities are
among the top ten factors. The following is a brief discussion of the
ranking of the factors and groups as deducted in Table 1 & 2.
Owner/Owner's representative related factors:
The result shows that the average of this group relative importance
index is (RII=65.51%) with the fourth position of the rank order among
the six groups as shown in Table 2. The top ranked factors are: Excessive change orders by owner, slow decisions from owner, and delay in handing over site.
Excessive change orders by owner ranked as the second
most critical source of claims. The respondents agreed that excessive
change orders by owner during project implementation is considered as
one of the main sources of claims caused by owners. An excessive number
of changes can disrupt a project and may require a significant change to
the contractor's means and methods of performing the work. With
excessive changes, the work scope may no longer closely resemble the
original contract work scope and the contractor will have to expend
additional time and resources to perform the changed work. Therefore,
the contractor will seek compensation for the losses incurred due to the
changes.
Slow decisions from owners is one of the significant
factors which rated at the sixth position. In most cases, slow decisions
from owner, is due to lack of proper coordination and communication
between owner and consultant or owner and contractor. So in this group
the contractor's respondents showed the high significance of this factor
in causing claims.
Consultants considered delay in handing over site as
one of the major issues in Indian construction projects. Most of the
respondents agreed to consider this factor as one of the highest
contributing factors to the generation of claims in Indian construction
projects.
The bottom ranked factors were: Long line of
authority in owner organization, acceleration and stop and go operation,
delay in approval of completed work, owner personality, and lack of
staff experience for contract provisions management. Most contractor's
respondents agreed that these factors have a moderate impact and
contribution to the generation of claims in Indian construction
industry.
Contractor related factors: Contractor related
factors were the highest ranked group with an average relative
importance index value of (RII=69.39%) as shown in Table 2.
This group is considered as the highest contributing group to the
generation of claims in Indian construction projects from the
consultant's perspective.
The respondents measured contractor’s financial
problem during project implementation as the number one source of claims
caused by contractor from the consultant's perspective. Most
consultants agreed that this issue affects the performance of the
projects and results in delay of the work progress and poor quality
performance. So in this group the consultants showed the very important
role of this factor in causing claims. Where it directs the contractor
and the owner to present claims against each other.
Poor planning and management by contractor rated
fourth. Some contractors hastily submit a plan of operation that their
field personnel do not intend to follow. What these contractors do not
realize that this schedule may be critical in demonstrating the impact
of a delay or disruption. In fact, an approved "fictitious" as planned
schedule may handicap the contractor's chances of discovering the
impact, communicating to the owner resolving the claim, or recovering
its unanticipated delay costs if the delay ends up as a dispute.
The respondents ranked delay caused by contractor in
the fifth position. Many causes contribute in delays caused by
contractor; delay caused by supervisor, delay caused by low experience
of contract management by contractor, delay in mobilizing resources,
delay in materials or equipments procurement or other issues. So the
consultants agreed strongly for this factor results in big problems in
construction projects, and if the contractor fails to complete the work
in the required time, the owner is entitled to make a claim against the
contractor for additional costs arising out of the contractor-caused
delay.
The respondents ranked lack of control over sub
contractors at the seventh position. Most consultants agreed that this
factor reflects the insufficient management skills of main contractor.
This perhaps link to lack of clear contractual framework and objective
criteria for engaging subcontractors in Indian construction projects.
Lack of control over subcontractor may lead to unwanted conflicts, low
productivity and development of negative attitudes on the site, which
eventually leads to delays which results in claims.
The latter factors: Poor quality of
contractor's work and execution errors by contractor have a relative
importance index span ranges from 55% to 62% which indicate that these
factors have a moderate contribution to the generation of claims.
Contract documents related factors: The
results indicate that the average of group 3 relative importance index
is (RII=65.66%) with the third position of the rank order among the six
groups. This group is considered as the third highest contributing group
to the generation of claims from the consultant’s point of view.
Variations in quantities between original and actual
quantities was the top ranked factor in this group and is considered as
one of the main factors resulting in claims. In large civil engineering
projects, variations can be very significant, whereas on small building
contracts they may be relatively minor. Variations may give rise to
additions or deductions from the contract sum. This may include not just
the work which resulted due to the variation, but other expenses that
incurred because of the variation, such as the impact on other aspects
of the works. Variations may also (but not necessarily) require
adjustment of the completion date.
The respondents ranked poorly written contracts and
ambiguities at the tenth position. Most consultants agreed that this
issue affected them when ambiguities were found in the provisions of
their contracts. It was found in some contracts ambiguous provisions led
to misunderstanding between contractor and the owner's representative,
which will end in a conflict leading to claims submission or disputes
between the parties involved in the contract.
The respondents also ranked design error or omission
at the thirteenth position. Consultants agreed that this factor has an
important role in causing claims in Indian construction projects.
Undefined scope from the beginning, frequent changes, and last minute
design changes to lower the cost of constructing the project prior to
bids opening. In some instances, budget and time constraints force
designers to compress design time. Consequently, they may not adequately
review the contract drawings or may not have the time or funds to
adequately coordinate the work performed by various design disciplines
prior to the bidding stage. So all these factors will definitely lead to
design errors and omissions and most consultants agreed that this will
lead to conflicts between contractor and owner's representative.
Incomplete contract documents, discrepancies between
contract documents, and different type of contracts were ranked at the
last in this group with relative importance index values ranges from 55%
to 66% indicating their impact ranges from low to a moderate.
Project related factors: This group of causes
have an average relative importance index value of (RII=61.46%) with the
fifth position of the rank order among the six groups as shown in Table 2.
The top ranked factor in this group is scope change of the project
which in overall claim causes ranked at the sixth position. When minor
changes in the scope of the work start escalating, the parties must
consider whether the contract in essence became a different contract
than was originally bargained for and a cardinal change has taken place
as this is can be considered one of the main sources of claims in Indian
construction industry. Most consultants agreed that "Change scope of
the project" affects significantly the project activities and results in
delay of work progress and performance.
The latter factors include complex execution of the project, different sub grade condition and change of project location.
Contractual relationship related factors: This
group of causes have an average relative importance index value of
(RII=65.66%) with the third position of the rank order among the six
groups as shown in Table 2.
The top ranked factors in this group are lack of
coordination and communication among parties, failure of participants to
deal promptly with changes and unexpected outcome, and awarding bid to
the lowest bidder. With respect to the first factor, Many contract
claims and disputes arise from lack of coordination and good
communication between the owner and the contractor or between the
contractor and the consultant, subcontractors or suppliers during the
time of bidding and during the execution of the project. So in this
group the consultants showed this factor as a highly important cause
resulting in claims. For the second factor insufficient time for bid
preparation and inadequate investigation before bidding. In the current
construction industry status in India, with the heavy budgeted and
complex projects, changes are inevitable, failure to deal promptly with
these changes may lead to big issues and problems that will affect both
parties and eventually resulting in claims and disputes.
The respondents ranked awarding bid to the lowest
bidder at the fourteenth position So most of the owner's respondents
have agreed on the moderate importance of this cause in the creation of
claims in Indian construction industry.
The bottom ranked factors were: Insufficient time for
bid preparation and inadequate investigation before bidding, suspension
of work by one party and termination of contract by one party. The
respondents agreed strongly that these factors are moderately
contributing to the generation of claims in Indian construction
industry.
External factors: The result shows that the
average of group 6 relative importance index value is (RII=58.62%) with
the sixth position of the rank order among the six groups as shown in Table 2.
This group is considered as the lowest contributing group to the
generation of claims. The top ranked factor in this group stakeholder
(beneficiaries, local community, authorities) interference. Consultants
considered this factor moderately contributing to the generation of
claims in Indian construction projects.
The respondents ranked the following factors:
Unexpected change in material price, unforeseen ground condition by all
parties, changes in government regulations and laws, unexpected changes
in exchange, interest, and inflation rate, extreme weather conditions,
and force majeure at the twenty-seventh, twenty- ninth, thirty-first,
thirty-fifth, thirty-seventh, and thirty-minth positions, respectively.
Consultants considered these factors of a less importance and
contribution in causing claims in Indian construction industry.
Claim types
The data collected from the third part of the
questionnaire were analyzed and the ranking of different types of claim
based on their frequency shows the top ranked claim type is extra work
claims. This means that extra-work claims are the most frequent type of
claims in Indian construction projects from the contractor's point of
view. Most of the consultants agreed to consider this claim type as the
most frequent claim type in Indian construction projects.
The respondents ranked at the second position delay
claims with a relative importance index value of (RII=76.85%). This
indicates that the frequency of occurrence of delay claims in Indian
construction projects is high.
The respondents ranked price escalation claims at the
third position with a relative importance index value of (RII=73.26%)
The consultants agreed that this type of claims occurred more frequently
in Indian construction projects. The consultants ranked changes claims
at the fourth position with a relative importance index value of
(RII=71.91%). Most of the consultants agreed that this type of claims
also occurs frequently in Indian construction projects, whereas the
respondents ranked different site conditions claims and on the other
hand, the respondents agreed to rank contract ambiguity claims,
different site conditions claims, disruption claims and acceleration
claims at the fifth, sixth seventh and eighth positions, respectively.
Most consultant's respondents agreed that these two types of claims have
a medium to rare frequency of occurrence in Indian construction
projects (Table 3).
Conclusion & Recommendations
The paper investigated the causes and the frequency
of different types of claims facing the Indian construction industry. A
questionnaire was designed and distributed to the consultants. From the
results, it was found that the most dominating claim group and source is
contractor related factors and the top ten most causes contributing to
the generation of claims are: Contactor financial problem, excessive
change orders by owner, slow decisions from owner, poor planning and
management by contractor, and delay caused by the contractor, change
scope of the project, lack of control over sub contractor, delay in
handing over site, variations between original and actual quantities,
and poorly written contracts and ambiguities. It can also be concluded
from this study that extra-work claim is the most frequent claims type
in Indian construction industry while delay claims were ranked second,
acceleration claims were ranked last, indicating that it is the least
frequent claim type in Indian construction projects.
In accordance with these results, the recommendations
set out from this research have been derived in a manner which makes
them feasible, tangible and can be acquired as steps and procedures.
Construction professionals may follow in order to avoid/mitigate and
manage their claims. Furthermore, this study was conducted in India and
the recommendations maybe generalized to an extent to construction
projects within the same industry in India. The essential steps project
parties can take to minimize/mitigate claims and deal with the
aforementioned identified.
For More Open Access Journals Please Click on: Juniper Publishers
Fore More Articles Please Visit: Civil Engineering Research Journal
Comments
Post a Comment